MEC is planning for a major overhaul of the Allen steam turbine at the CHP plant in Maabjerg, Holstebro, Denmark. The unit is a 32 MW twin cylinder condensing turbine commissioned in 1992. To ensure reliable, safe, and efficient operation of the unit a major overhaul of the low-pressure turbine, the reduction gear and generator is needed. For a more thorough description of the Works included in this call for tender, please see the Technical Specification, Appendix 1. Included in this call for tender are also several optional deliveries. For a description of the options, please see section 4 in the Technical Specification, Appendix 1. Purchase or realization of the options are predominantly dependent on the actual findings.
Dette er et begrænset kildeudsnit. Se fuld beskrivelse, dokumenter, rettelser og aktuelle betingelser i originalen.
Åbn det oprindelige udbudKendte frister
- Anmodning om deltagelse12. aug. 2026
Fristerne er ikke knyttet til bestemte delaftaler i dette kildeudsnit. En fremtidig frist er ikke en samlet vurdering af hele procedurens status.